๐ฐLDSN 002

Latest DyingStar News: LDSN 002
Here's the latest project progress updates from the past few days.
VFX
- The team is progressing slowly.
- The creation of the sandstorm (fluid mechanics) is slow, but we should have the first visuals in a few days. A lot of optimization work to be done.
- VFX on the Sandbox planet needs to be done, and the lore needs to be updated. The Lore team must present the lore to the leads.
AUDIO
- Work on Steam Audio in progress
- Work on wwise also in progress
WEBSITE
- The issue list is finalized (news last week)
- Deployment by this weekend (v1: news + issues)
- A maintenance system will be designed
- Document to be included on the website to indicate what to publish on it
GAME DESIGN / LEVEL DESIGN
- Order for carts and modules sent to 3D completed
- Waiting for the Lore to continue with the gameplay
3D / ART
- Packages / crates: progressing, order to have quite a few creations, final vote on crates soon to be launched
- Sandbox elevation map in progress
- Order for carts and modules received, beginning to understand the modules, briefs lacking a little precision (ambiguous sentences)
- They will start with the modules, calls for creation Next week, hopefully
- Container sizing issues in height and length
- New people have arrived in the last few days
- Discussion with Lore about ARES creation (logo, etc.)
- Discord is difficult when people arrive to give them information
LORE
- They're progressing pretty well
- Quite a few things have been defined at the ARES level
- Same for Sandbox, Sandbox sizing is in progress
- The organization is being defined well within the teams
- Team leaders are currently being chosen
PLANET TECH:
- Planet with a radius of 500 km, some issues still on the Horizon side before working on the planet
- Player repair on the planet
- ddurieux offers to build the train
- Waiting for Horizon to continue the tasks
- Need to strengthen the team
UI
- They didn't do anything ๐
- Vosne worked on the website
NETWORK:
- GORC integration in progress (started 2 or 3 days ago)
- Services defined, tasks will be added to project management
Project information LDSN
DDddurieux10/10/25